Return to Map

LOW IMPACT
SR 502 Both Directions - SR 502 Widening from I-5 to Battle Ground(MP 0.59 to 6.61) Monday, July 28 to Friday, Aug. 1: Multiple, daytime, and nighttime, intermittent, single-lane closures with flaggers, throughout the 6 mile length of the project limits, from 9 a.m. to 3 p.m. daily & 6:30 p.m. to 6 a.m., nightly. Friday, July 25 to Thursday, July 31: Multiple, nighttime, intermittent single-lane closures with flaggers, on NE 29th Avenue through NE 219th Street. from 6:30 p.m. Friday, July 25 to 6 a.m. Thursday, July 31. Last Updated: 7/28/2014 9:08 AM
From milepost 1 to milepost 7
Report Detail: Project Engineer: Chris Tams, Phone: (360) 759-1310 This project widens SR 502 and adds median barriers, 10-foot shoulders for bicycles and pedestrians, and traffic signals. For more information please contact the project office.