Return to Map

MODERATE IMPACT
I-90 Both Directions - I-90 Snoqualmie Pass milepost 61 to 65: Drivers can expect single lane closures both directions Tuesday through Thursday from 10 p.m. until 9 a.m. the following morning. Last Updated: 8/31/2014 10:01 AM
From milepost 61 to milepost 65
Report Detail: I-90 / MP 61 (Price Creek) to MP 65 – Paving Project Description: This project provides for the improvement of 3.54 miles of I-90 in Kittitas County from milepost 62 to 65.54. Work will include removing the existing asphalt surface and repaving. Other work will consist of striping, guardrail and other safety items. Contact: Jeff Minnick, Project Engineer, 509-577-1810 Construction Begins: Spring 2014 Scheduled Completion: Fall 2014