Return to Map

LOW IMPACT
I-5 Northbound - I-5, Northbound, Gee Creek Rest Area, Discovery Corridor Wastewater Transmission System (milepost 10.75) Traffic Impacts: Monday, July 28 to Friday, Aug. 1: Daytime narrow lanes with temporary striping and barriers at the entrance of the Gee Creek Rest Area for sewer line installation. NOTE: There will be intermittent shoulder closures on both directions of I-5 between mileposts 11.47 and 13.82 from Friday, July 11 to Friday, August 15. Last Updated: 7/25/2014 10:55 AM
At milepost 11
Report Detail: Construction Manager: Ron Monteferrante, Phone: (360) 993-8851 This project adds a new wastewater conveyance pipeline to connect the City of Ridgefield's Interstate 5 Junction area to Salmon Creek Treatment Plant. It will increase Ridgefield's wastewater capacity in support of future industrial and commercial development and help provide efficient, high-quality sewer service at the lowest possible cost. For more information, contact the project office.