MODERATE IMPACT
SR 508 Both Directions - Thursday, March 28, 2019: Contractor crews will shift traffic from the original 1930 structure to a single lane of the new bridge. Traffic will alternate through the single lane, around-the-clock using a temporary traffic signal,while bridge replacement work continues. Both directions of the new two-lane bridge are scheduled to open in April after final paving, guardrail and pavement markers are installed. Last Updated: 3/29/2019 11:54 AM
From milepost 13 to milepost 14