LOW IMPACT
US 12 Both Directions - US-12 both directions milepost 142 to 164, White Pass: Tuesday July 14 through Friday July 17, traffic should be prepared for flaggers alternating one-way traffic or for one-way piloted traffic control during daylight hours. Traffic should anticipate up to 20 minute delays. Last Updated: 7/11/2020 7:51 PM
From milepost 142 to milepost 164
Report Detail: White Pass Vicinity Major Drainage Phase 2 Contact: Jerry Wood, WSDOT Project Engineer, 509-577-1859 Project Description: This project provides for the improvement of US-12 in various locations by installing drainage structures and new culvert pipes including underdrains, modifying existing drainage structures; replacing riprap and quarry spalls, extruded curb, pavement markings and delineation. This project is dues to be completed by Fall 2019