Eastern Region CCTV Systems - New Installs - Complete June 2019

Project news

Project awarded to Power City Electric, Inc.

Needs & benefits

Two new CCTV system cameras were installed spring and summer. The first camera was installed at US 2 and North Access Rd. (Costco) intersection. The second camera was installed at US 395 and Wandermere Rd. intersection.

Timeline

Project was completed in mid-June.

Funding

  • PEF (Pre-Existing Funds) - $180,966
  • Total - $186,966

Contact

Mark Allen, project engineer
2714 N. Mayfair St. 
Spokane WA, 99207
(509) 324-6232

Location of new CCTV camera installations