Eastern

I-90 - SR 21 to Ritzville - Paving - Complete November 2019

Needs & benefits

This project will restore 9.9 miles of the existing asphalt pavement by grinding and placing 0.15 foot depth of asphalt on the driving lanes and shoulders. The project will extend between the Lind and Ritzville interchanges.

Timeline

Construction began on April 15. All contract work was completed the week of June 10. Minor items remain.

Funding

Financial Data for PIN 609020I
Funding Source Amount ($ in thousands)

  • Pre-Existing Funds (PEF) - $8,036
  • Total - $8,036

SR 26 - Washtucna to LaCrosse - Airport Rd - Chip Seal

Project news

This project was awarded to Central Washington Asphalt Inc.

Needs & benefits

These sections of the chip seal will rehabilitate existing bituminous pavement to preserve and maintain pavement structure. All sections will receive bituminous surface treatment, fog seal and rumble strips. Not all sections, but most will receive crack seal, pavement repair, prelevel, and guardrail. 

Timeline

The project is expected to begin May 28 and be completed in September 2019.

US 395 - Bridge Pier - Redirectional Landform Mitigation

Project news

The Washington State Department of Transportation (WSDOT) will be working with contractors during the summer and fall of 2019 around the region to update and repair guardrail and other roadside safety items.

Needs & benefits

This project updates and repairs existing safety features currently in place along several routes in Eastern Washington. Guardrail will be raised and upgraded, redictional landforms around piers will be removed and replaced with a barrier. Guardrail end treatments will be upgraded to new crashworthy terminals.

I-90 - Bridge Pier - Redirectional Landform Mitigation

Project news

The Washington State Department of Transportation (WSDOT) will be working with contractors during the summer and fall of 2019 around the region to update and repair guardrail and other roadside safety items.

Needs & benefits

This project updates and repairs existing safety features currently in place along several routes in Eastern Washington. Guardrail will be raised and upgraded, redictional landforms around piers will be removed and replaced with a barrier. Guardrail end treatments will be upgraded to new crashworthy terminals.

Eastern Region CCTV Systems - New Installs - Complete June 2019

Project news

Project awarded to Power City Electric, Inc.

Needs & benefits

Two new CCTV system cameras were installed spring and summer. The first camera was installed at US 2 and North Access Rd. (Costco) intersection. The second camera was installed at US 395 and Wandermere Rd. intersection.

Timeline

Project was completed in mid-June.

Funding

  • PEF (Pre-Existing Funds) - $180,966
  • Total - $186,966

US 2 - Reardan to Espanola Rd - Paving - Complete June 2019

Project news

Awarded to Shamrock Paving Inc. on December 26, 2018, for $2,222,222.

Needs & benefits

This project will restore 7.6 miles of existing asphalt pavement by grinding and place 0.15 foot depth of asphalt on the driving lanes. The project will extend west of the City of Reardan and end at Espanola Rd.

Timeline

The project was substantially completed on June 12. All corrective items addressed and the project is now complete.

Funding

Financial Data for PIN600226N
Funding Source Amount ($ in thousands)

US 195 - SR 271 to Plaza RD - Paving

Project news

A portion of US 195 traffic will be impacted during summer 2019. Roadway surface is rehabilitated from Rosalia to Plaza Rd using hot mix asphalt. The work will have potential short term traffic delays for roughly two months. The project was awarded to Shamrock Paving, Inc. on March 1, 2019.

US 195 - Smythe Rd to Paradise Rd - Decreasing Lanes Only - Paving - Complete May 2019

Project news

US 195 traffic will be impacted late spring 2019, to summer 2019 while the roadway surface is rehabilitated.  The work will take place approximately 10 miles south of the City of Spokane and have potential short term traffic delays for several weeks.

Needs & benefits

Northbound lanes of this divided section of highway are constructed of Portland Cement Concrete pavement, which remains in serviceable condition.

I-90 - Geiger Interchange Improvements

Project news

This project is currently in the traffic analysis phase. During this phase, different alternatives will be considered and a preferred option will be selected based on the needs of the interchange identified in the analysis. Construction is funded in the "Connecting Washington" package. WSDOT plans to advertise this project for construction bids in late 2019.

I-90 - Sprague Ave I/C to Argonne Rd I/C - Paving

Project news

All bids were rejected on April 25. Project is scheduled to be repackaged and resubmitted for advertisement on November 18.

US 2 - Colbert Rd to Westwood Rd - Paving

Project news

The project was awarded to Inland Asphalt Co. on February 25.

Needs & benefits

This project is located on US 2 between MP 299.74 and 306.01 in Spokane County. This project involves bridge deck repair, hot mix asphalt, grinding and paving. It also includes the installation of guardrails and rumble strips. 

This project will rehabilitate the existing pavement to preserve the pavement structure while achieving the lowest life cycle for pavement service life.

US 2 - Division Wye to Farwell Rd - Paving

Project news

Located on US 2 (N. Newport Hwy) within the city of Spokane and Spokane County, this pavement rehabilitation project begins at the Division Wye and extends to Farwell Road. Grinding and paving almost two inches of hot mix asphalt is intended to preserve the pavement structure below and provide a newer, smoother ride.

The project extends through five signalized intersections:

US 2 - Hayford Road to Deer Heights Road - Median Channelization - Complete June 2019

Project news

The project was awarded to Cameron-Reilly, LLC on March 15. The center two-way, left-turn lane in the vicinity of the project will be closed for the duration of the project. 

Needs & benefits

Revises the channelization and illumination near Hazelwood Road in Airway Heights.

Timeline

Work began April 15 and has been completed. No further work is scheduled.

Funding

Financial Data for PIN 69960I

  • Pre-Existing Funds (PEF) - $329,706
  • Total - $329,706

US 195 - Thorpe Rd Intersection Improvements

Project news

Construction at Thorpe Road for intersection improvements are complete. 

Needs & benefits

This project is located on US 195 between MP 94.44 and 95.44 in Spokane County. The project will involve hot mix asphalt paving, illumination, and guardrail improvements. This project will also be constructing a new feature for our area called "J-Turns".

I-90 - US 2 Garden Springs to Broadway Ave - Ramp Meters

Project news

Traffic may soon move a little more smoothly around Spokane with the help of a new ramp meter that will manage the flow of vehicles merging onto I-90. Currently, one ramp meter is installed as drivers head north on US 195 and merge onto eastbound I-90. Five new ramp meters are set to go to ad on December 2. Construction is expected in 2020. Locations for eastbound I-90 ramp meters include:

Pages